top of page

​



​

How to Submit a SIP for Olds, Alberta

Go to Alberta Utilities Commission
  1. Click: ‘Access Here’ on the Access to the eFiling System

  2. Create a New Personal Account

  3. Login to your email to confirm the account

  4. Login and Continue to eFiling

  5. In the ‘Go To’ search bar, search for: 30732

  6. Click ‘Register’ to participate and acknowledge and agree to the AUC privacy policy and select ‘Intervener’ as your ‘Registration Type’

  7. Fill in the Statement of Intent to Participate and Save to submit

Submit a Statement of Intent to Participate (SIP) to the Alberta Utilities Commission (AUC) to explain why the proposed data centre and power plant should not be located within town limits.

Please Note

  • You do not need to live within the 1,000 m buffer zone to file a SIP (you can leave that section unselected).

  • The AUC will focus primarily on impacts of the proposed thermal power plant.

  • Anyone can submit an SIP, regardless of location.

  • The AUC site is not suited for cell phones - we encourage people to use a laptop for an easier SIP submission

Synapse Data Centre

The Synapse Data Centre project, proposing a ~1 GW AI data centre campus and a 1.4 GW natural gas power plant on roughly 300 acres (121 hectares) has drawn strong opposition in Olds because of its close proximity to residences.

The Alberta Utilities Commission (AUC) rejected the initial application in March 2026 due to deficiencies. Synapse has since reapplied and the new submission is under review.

It is argued that the project is unsuitable for its in-town location near homes, an agricultural college, wetlands, and farmland for these key reasons:

  1. Proximity to residential areas and incompatible zoning

  2. Noise concerns, including infrasound and backup generators

  3. Air pollution and emissions from the gas plant

  4. Insufficient Emergency Preparedness Plan and lack of consultation with county and emergency service providers

  5. Limited public consultation and transparency

  6. High water demand and resource strain

  7. Incomplete environmental and impact assessments

  8. Traffic, infrastructure, and municipal capacity pressures

  9. Project scale and long-term risks outweigh local benefits